![orange-squares orange-squares](https://onsite3d.ca/wp-content/uploads/elementor/thumbs/orange-squares-qmkd555gfoq6x60i7qe9gjldu3y1u7bakjp61nl26q.png)
Water Injection and Flare System Upgrades
This MOC project was completed over (3) separate phases and
involved bringing in a water injection package, new production, new
inlet separator, upgrades to the treater system and new flare system. Site scans allowed us to capture existing as-built conditions and all new/surplus equipment was scanned before digitally placing in the site. Once constructability was completed with engineering and operations all piping/structural was pushed to pre-fabrication with less than 1% rework ahead of (2) scheduled outages.