The project focused on the reactivation and integration of the Leland Sweetening Plant (LSP), which had been shut down since 2015, with the Horse Gas Plant that was operational. This integration aimed to de-bottleneck the Horse plant by utilizing the mothballed refrigeration skid, inlet separation, and flare systems of the LSP. Two options were evaluated: continuing as two separate plants or fully integrating the Leland Plant into the Horse Plant.
The project sought to increase the total processing capacity by 1700 e3m3/d and involved evaluating equipment needs, facility layouts, and flare system optimization. Key objectives included a planned startup by May of 2025. This integration presented an opportunity to leverage existing infrastructure and enhance the overall capacity and efficiency of the gas processing facilities.